A bathroom is small, but it holds more trades per square foot than any other room in the house. Here is how a bathroom renovation runs, step by step, and what to watch for so you only do it once.
How long a bathroom renovation takes
A standard 3-piece bathroom with the same layout usually takes about 2 to 3 weeks of work. Moving the toilet, shower or vanity, or adding a bathroom, adds about 1 to 2 weeks depending on the size, because the plumbing changes and the permit add steps.
The steps, in order
- Demo down to the studs and subfloor
- Framing and any plumbing or electrical changes (rough-in)
- Waterproofing the shower or tub area and the floor
- Tile
- Vanity, toilet, tub or shower glass, fixtures, lighting and the fan
- Paint and final clean

What happens at each step
Demo
Everything comes out down to the studs and subfloor. This is when we check the subfloor and joists under the tub and toilet for water damage, which is common in older bathrooms.
Rough-in
New drain lines, water lines, venting and electrical go in. If the toilet, shower or vanity moves, this is where it happens. Inspections are done before the walls are closed.
Tile
Walls and floors need to be flat for tile to look right, especially large-format tile. Prep is most of the work.
Fixtures and finishing
The vanity, toilet, tub or shower glass, faucets, lighting and the exhaust fan go in. The fan should vent outside to get the moisture out of the house.
Waterproofing: the step you never see
This is the step that matters most. Behind the tile, the walls and floor around the shower get a waterproof membrane so water can’t reach the framing. Skipping or rushing it is how bathrooms end up with rot and mould a few years later.

Upgrades worth thinking about
- Heated floors. See our post on heated bathroom floors
- An ensuite. See our ensuite renovation guide
- A bathroom in the basement. See adding a basement bathroom
- Accessibility features like a walk-in shower and grab bars. See our accessible renovations guide
Do you need a permit to renovate a bathroom in Toronto?
- Replacing fixtures in the same spots doesn’t need a building permit
- Adding a bathroom, moving plumbing or changing walls does
- Electrical changes get reported to ESA by a licensed electrical contractor
Real job: a primary ensuite in Brampton

The old ensuite had a built-in tub deck, a dated vanity and small floor tile. We took it back to the studs and rebuilt it with a freestanding tub, a glass shower with a recessed niche, a double vanity with a lit mirror and large marble-look tile on the floors and walls.

Mistakes we see
The big one is hiring unlicensed trades. We often get called to redo bathrooms where the rough-in plumbing or the waterproofing wasn’t done properly, which means tearing out new tile to fix it.
Questions we get asked
How long does a bathroom renovation take in Toronto?
About 2 to 3 weeks for a same-layout 3-piece, plus 1 to 2 weeks if the layout changes.
Do I need a permit to renovate a bathroom?
Not to replace fixtures in the same spots. Yes if you add a bathroom, move plumbing or change walls.
Can I use my house during a bathroom renovation?
Yes. If it’s your only bathroom, plan for the days it’s out of service.
Getting quotes? Read our 10 questions to ask before you hire a contractor first.
Planning a bathroom?
Send us a few photos of your bathroom and we’ll tell you what it takes. Site visits are free. See our bathroom renovations page or the bathroom renovation cost guide.
Want a rough number first? Try our free renovation budget calculator, then map out the job with our renovation planner. Our free GTA renovation guide covers the rest.
Call 416-995-4534, email Info@905reno.ca or book a free site visit. We stand behind every space we build.